Construction to Begin at the Intersection of Claribel Road and Roselle Avenue

Stanislaus County Public Works will begin construction on the intersection of Claribel Road and Roselle Avenue on Monday, October 15, 2018. The work to be done will include construction of road widening to accommodate turn lanes, and the installation of a traffic signal at the intersection.

Why the change

This project is located at the intersection of Claribel Road and Roselle Ave, which has continually become more congested. The construction of a signalized intersection will increase public safety, allow improve traffic flow, and increase operational efficiency.

ATTENTION: UPCOMING LANE CLOSURES March 14th to 15th

Thursday, March 14th to Friday, March 15th please use alternate routes and avoid the area as there will be lane closures and flaggers onsite directing traffic. Paving and lane shifts are to occur on Claribel Road going both north and south, and congestion within the area is expected. Avoid the area if at all possible.

Key Project Dates

Project start: 10/2/18
Grading/earthwork: 10/17/18
Storm drain work: 10/20/18
MID irrigation crossing: 11/1/18
Finish grading: 11/14/18
Aggregate base: 11/27/18
Asphalt paving: 12/10/18
Signal pole placement: 2/19/19
Project finish: 4/17/19