Construction to Begin at the Intersection of Claribel Road and Roselle Avenue

Stanislaus County Public Works will begin construction on the intersection of Claribel Road and Roselle Avenue on Monday, October 15, 2018. The work to be done will include construction of road widening to accommodate turn lanes, and the installation of a traffic signal at the intersection.

Why the change

This project is located at the intersection of Claribel Road and Roselle Ave, which has continually become more congested. The construction of a signalized intersection will increase public safety, allow improve traffic flow, and increase operational efficiency.

Questions or Comments?

Feel free to call us at 1-800-229-8553 or fill out this online form and we will get back to you.

Submit the Form

Key Project Dates

Project start: 10/2/18
Grading/earthwork: 10/17/18
Storm drain work: 10/20/18
MID irrigation crossing: 11/1/18
Finish grading: 11/14/18
Aggregate base: 11/27/18
Asphalt paving: 12/10/18
Signal pole placement: 2/19/19
Project finish: 4/17/19

Project Location

Recent Project Photos